Monday, March 19, 2007

Done

So that is it. Next stop, Launch 2007!



Thanks to everyone who visited this Blog and for all those who gave feedback. And a especially big thanks to Bruce Tennant for his regular contribution of photo's.

According to Hugh's report on Sunday evening, everything is complete as per the contract. We still have many tasks to do such as installing the zinc anodes on the sheet pile, installing the mast stepper on the new base, building and installing the new gangway for the launch pad area, preparing additional electrical boxes for the new docks, installing the pump-out station, pounding over 100 pilings, launching the docks, including new ones, and then installing the services everyone expects. WOW! That is quite a list and no doubt there are other things to do.

Needless to say, this all cannot be done by two, or even 10, people. We are a volunteer club and to have a timely launch, with berths ready to go for the warm weather, we will all have to work together.

The budget for 2007 has been completed, the fixture card will be available soon and John Boyd starts in two weeks. Please consider how you would like to participate and then contact the appropriate director. To see a list of the directors and their contact information, click HERE.

Thanks again for visiting, and have a Great Summer!
Greg

Photo's Bruce




Monday, March 12, 2007

Update

We walked down to the Breakwater last evening. It is very nice that the weather has warmed up enough to comfortably get out in the evening. Now with the later sunsets, we will be able to work on our boats longer. I find sailors get a little fidgety when things start to melt and the snow disappears off the boat covers. I know, they are forecasting snow on Thursday, but I guy can dream!?! If you haven't made it down to the project lately you probably haven't seen all the cement that has been poured over the past couple of weeks. And by the looks of it much of it will never be seen again. I am speaking of the sheet pile support blocks that are tied with a long metal rod to the back of the sheet pile. The are substantial. Once they are buried, they will be out of sight. The one large cement block that will be seen for a long time is the foundation for the gangway. There was an interesting phenomenon we saw last evening. The 80% of the ice in the inner harbour was covered with water - probably 6 or 8 inches. It must have been run-off as it was muddy coloured. It was flowing across the ice near 'A' dock and running into a crack in the ice beside the wharf. When I get an update from the Breakwater Committee, I will post it here. From a major construction point of view things are starting to wind down. We will see more detail work being done. If anyone has any interesting photo's, please don't hesitate to send them to me.

Friday, March 2, 2007

Launching Pad

The Sheet Pile has been driven into place, never to move again! They have anchored it back to a huge concrete block that has been poured in place. You will see the tie rods that stretch from the sheet pile, back about 25 feet, to the block. It will all be buried soon. We won't see the concrete block. This is where the boats will be launched, the mast stepper will be installed, and the gangway down to the floating docks (dock "C" maybe?) will be attached.

Bruce provided the photo's. The dates they were taken can be see superimposed on each picture. In this post it goes from newest to oldest.


Pouring Cement. They insulated it after they were done. It generates enough heat that is sets properly as long as it is insulated.


The vertical green pipe is for the mast stepper.




The sheet pile looks nice and straight in this shot


Some finishing touches.


The sheet pile was very ragged across the top edge before they cut it level.