Saturday, April 14, 2007
RYC News
http://rycnews.blogspot.com/
Otherwise please enjoy an archive of our 2006/2007 Breakwater Project blog.
Regards,
Greg
Monday, March 19, 2007
Done

Thanks to everyone who visited this Blog and for all those who gave feedback. And a especially big thanks to Bruce Tennant for his regular contribution of photo's.
According to Hugh's report on Sunday evening, everything is complete as per the contract. We still have many tasks to do such as installing the zinc anodes on the sheet pile, installing the mast stepper on the new base, building and installing the new gangway for the launch pad area, preparing additional electrical boxes for the new docks, installing the pump-out station, pounding over 100 pilings, launching the docks, including new ones, and then installing the services everyone expects. WOW! That is quite a list and no doubt there are other things to do.
Needless to say, this all cannot be done by two, or even 10, people. We are a volunteer club and to have a timely launch, with berths ready to go for the warm weather, we will all have to work together.
The budget for 2007 has been completed, the fixture card will be available soon and John Boyd starts in two weeks. Please consider how you would like to participate and then contact the appropriate director. To see a list of the directors and their contact information, click HERE.
Monday, March 12, 2007
Update
Friday, March 2, 2007
Launching Pad
Bruce provided the photo's. The dates they were taken can be see superimposed on each picture. In this post it goes from newest to oldest.


Pouring Cement. They insulated it after they were done. It generates enough heat that is sets properly as long as it is insulated.


The vertical green pipe is for the mast stepper.


The sheet pile looks nice and straight in this shot

Some finishing touches.

The sheet pile was very ragged across the top edge before they cut it level.
Tuesday, February 20, 2007
Sheet Pile
orientation of this section is north-south.
Friday, February 16, 2007
Bi-Law Committee Update (And Breakwater Pictures)
The Bi-Law committee met for the 3rd time last evening. It was nice that we were able to get the 5 committee members all together! Our next meeting is scheduled for March 25. Everyone seems to feel we are making positive progress on the review, and to quote George: "My initial thoughts were that this was going to be a laborious task of going through a bunch of 'legaleze' but I've found the discussions to be excellent, with full input from everyone." If the work to date is any indication, the Board and membership will see positive results from the effort put into the process by the committee.
Breakwater...
Any of you who has been down to the wharf will have seen a lot more activity. Irving Equipment has set-up to begin installing the sheet pile.
I understand from Bruce (who provided the photo's) that it was really blowing down there - and as many of us know, that is nearly a 10 mile stretch of open ice - not much to slow it down!
Hey, what happened to Long Island - I know it's out there somewhere! I wouldn't be surprised if they saw
a couple of ice shacks scooting by...
road in front of the club!?!
Thursday, February 15, 2007
Breakwater Update
Here is the latest from Hugh Scarth:
- Anchor Blocks are being installed. 5 of the 7 have been completed
- Sheet Pile is going to begin soon
- They do not work in temperatures below -20C due to risk of damage to equipment
- There will be installed a 12" vertical pipe for the mast stepper prior to back filling around the Sheet Pile
- The mast stepper will need to be re engineered to work with the new base and it is expected that a stay system will be used to support it. The good news is due to the location of the stepper, the guy wires should not be in the way.
I noticed some activity down at the site today. It was quite a shock to see a crane on the wharf - Last time I saw that there were boats too - but not today. I think they are getting prepared to begin the installation of the Sheet Pile (but I will confirm that).
Progress as of Feb 12. The end 1/3 of the breakwater is at
the final height and will extend, at this height, to the where
the pavement ends at the road.
Wednesday, February 7, 2007
Photo Update - From Bruce Tennant
We have an RYC Board meeting scheduled for Sunday evening and there will be an update on the project provided at that time. I will pass on what I learn, via the Blog, early next week.
So the Shubenacadie Sam didn't see his shadow. I know sailors aren't superstitious so we don't need to worry about that anyway. Environment Canada did announce last week that the temperature was going to be colder in February, and "average" for the period February to April, so I guess that means March and/or April will be warmer than usual. Now, I took a look at Environment Canada's web site and they indicate they are right with their 3 month forecast between 45% and 50% of the time. I have also heard that the Groundhog is right around 40% to 50% of the time. Hmmm?!?

Looking at Kennebecasis & Mather Islands and the
Kingston Peninsula off across the ice.
Nice photo Bruce! The clouds don't seem real.

You can see one of the forms for the concrete pad
to the right of the worker

Behind the machine; that should be the finished
height. Wow, pretty impressive!

That should cut down on the waves and the wind.

What is the old saying? "Measure twice, cut once!"
Thursday, February 1, 2007
Concrete Pad Installation
In the photo's below we see them working on the second of 7 pads. The light base has already been poured.

Ever so slightly, you can see the bales of hay at the
end of the breakwater. They are there to insulate the Pad
that has been installed as the foundation for the
breakwater navigation light

A form for the concrete pad. Note the rebar in the box.
It is there for future attachment points

Pouring concrete out here is a multi-step process

Once the concrete hardens, the excavator will place
armour stone around the blocks to further secure
them within the breakwater structure
Monday, January 29, 2007
Progress Comparison & J24's


Photo Update - From Bruce Tennant
Thursday, January 25, 2007
The Bitter End - Armour Rock Begins
Thanks for the photo's. How thick is the ice, Bruce?
So, should it be Armor or Armour? Can anyone help with that?
And in case you missed it, there was a Breakwater Committee update on Jan 18. (Click to Link)

Better adjust your waypoints for those foggy trips back
from Scouts Beach. Grey Rocks, Grey Fog, Grey Goose
- a recipe for disaster!

They have brought in the heavy equipment. Nice angle
of the photos, Bruce. That's a long walk out there!

Wanted: Man with a delicate touch!

I understand they built the pyramid's by hand. Judging
by the water temperature, that would explain why there
are no pyramid's on the Kennebecasis.