In the photo's below we see them working on the second of 7 pads. The light base has already been poured.

Ever so slightly, you can see the bales of hay at the
end of the breakwater. They are there to insulate the Pad
that has been installed as the foundation for the
breakwater navigation light

A form for the concrete pad. Note the rebar in the box.
It is there for future attachment points

Pouring concrete out here is a multi-step process

Once the concrete hardens, the excavator will place
armour stone around the blocks to further secure
them within the breakwater structure