Here is the latest from Hugh Scarth:
- Anchor Blocks are being installed. 5 of the 7 have been completed
- Sheet Pile is going to begin soon
- They do not work in temperatures below -20C due to risk of damage to equipment
- There will be installed a 12" vertical pipe for the mast stepper prior to back filling around the Sheet Pile
- The mast stepper will need to be re engineered to work with the new base and it is expected that a stay system will be used to support it. The good news is due to the location of the stepper, the guy wires should not be in the way.
I noticed some activity down at the site today. It was quite a shock to see a crane on the wharf - Last time I saw that there were boats too - but not today. I think they are getting prepared to begin the installation of the Sheet Pile (but I will confirm that).
Progress as of Feb 12. The end 1/3 of the breakwater is at
the final height and will extend, at this height, to the where
the pavement ends at the road.